Barkham Bridge
Project details
Construction of a new bridge and road over the river brook.
Client / Contractor
Balfour Beatty
Programme
40 weeks (split over 2 phases)
Location
Barkham, Wokingham
November 2019 – January 2021
Period
Subcontract
NEC Option B re-measure
Scope of Works
- Earthworks for roads & piling platforms – 8000m3 cut or fill
- Construction of new swales & watercourses, including bagwork scour swales & brick wiers
- Drainage in existing road, within tight traffic management & significant number of services
- Kerbs & edgings
- Temporary sheet piling to river banks
- Pile cropping
- River diversion / over pumping, widening & deepening of river bed & construction of flex bag river banks