Luton DART
Project details
Client / Contractor
VolkerFitzpatrick Kier JV
Programme
112 weeks
Location
Luton
October 2018 – December 2020
Period
Subcontract
Bespoke (FIDIC) re-measure
Scope of Works
- Earthworks for piling platforms, viaduct pile cropping, Airport Approach road diversion 2 & 3, Gateway Bridge build area earthworks and groundworks, Airside Perimeter Track road realignment, Trough / Running Slab / Viaduct/ East Abutment / Parkway station drainage, 6N earthworks to East Abutment Gateway Bridge, various kerbing across all sites.
- Drainage – approx 2700m & 100no chambers across all sites
- Running Slab Drainage (1-5m deep)
- Trough Drainage (1-2m deep)
- Viaduct Drainage (2-5m deep) (Adjacent to NR fence/ boundary)
- Parkway Station Drainage (1-3m deep)
- Airport Approach Road Drainage (1-2m deep)
- Various drainage diversion including airside taxiway works (3-5m deep)