Luton DART

Project details

Client / Contractor

VolkerFitzpatrick Kier JV

Programme

112 weeks

Location

Luton

October 2018 – December 2020

Period
Subcontract

Bespoke (FIDIC) re-measure

Scope of Works
  • Earthworks for piling platforms, viaduct pile cropping, Airport Approach road diversion 2 & 3, Gateway Bridge build area earthworks and groundworks, Airside Perimeter Track road realignment, Trough / Running Slab / Viaduct/ East Abutment / Parkway station drainage, 6N earthworks to East Abutment Gateway Bridge, various kerbing across all sites.
  • Drainage – approx 2700m & 100no chambers across all sites
  • Running Slab Drainage (1-5m deep)
  • Trough Drainage (1-2m deep)
  • Viaduct Drainage (2-5m deep) (Adjacent to NR fence/ boundary)
  • Parkway Station Drainage (1-3m deep)
  • Airport Approach Road Drainage (1-2m deep)
  • Various drainage diversion including airside taxiway works (3-5m deep)