Magna Park South S278 Works, WP3, Foul Rising Main & Pump Station

Project details

Construction of new roundabout, private roads and 3km foul rising main & pump station.

Client / Contractor

VolkerFitzpatrick Ltd

Programme

52 weeks

Location

Magna Park, Lutterworth

January 2020 – January 2021

Period
Subcontract

NEC Option A lump sum

Scope of Works

S278 Works;

  • Earthworks – 9000m3 cut & 17000m3 engineered fill excavated from a borrow pit
  • Drainage – 1200m
  • Ducting – 6000m
  • Kerbs & edgings – 3000m
  • Culvert extension – Stream over pumping diversion, culvert units lifted in with crane on night shift road closures
  • Grasscrete

WP3;

  • Ducting & utilities – 6700m
  • Kerbs & edgings – 6000m

Foul rising main & pump station;

  • Earthworks to pump station – 4500m3
  • Foul rising main civils works including service crossings – 3000m
  • 5m deep foul manhole, connection onto existing live foul, in the road, over 24hr working weekend possession
  • 5m deep foul manhole connection at pump station
  • 600mm dia. 5m deep foul drainage at pump station
  • 3.6m dia. 5m deep wet well chamber
  • 2m dia. weholite pipe tanks