Magna Park Corby Enabling Works

Project details

Pump station, rising main, ducting, footways, surface water outfalls.

Client / Contractor

VolkerFitzpatrick Ltd

Programme

50 weeks

Location

Kettering Road / A43, Corby

July 22 – Jan 24 (2 visits)

Period
Subcontract

JCT re-measure

Scope of Works

Construction of foul pump station including;

  • 7.5m deep 2.4m dia wet well
  • Inlet & valve chambers
  • Foul drainage 5m deep
  • 2no 16m long storage tanks 5m deep
  • Brick perimeter wall & concrete yard slab
  • Foul rising main, chambers and connection – 1km with significant existing services, working in lane closures on the A43
  • Foul rising main connection into Anglian Water live foul sewer 6.5m deep
  • Street lighting ducting, column sleeves and chambers (1600m)
  • Footways (5000m2)
  • Edgings (2500m)

Surface water outfalls;

  • Gabion reno mattresses
  • MSE flex bagwork headwalls