Magna Park Corby Enabling Works
Project details
Pump station, rising main, ducting, footways, surface water outfalls.
Client / Contractor
VolkerFitzpatrick Ltd
Programme
50 weeks
Location
Kettering Road / A43, Corby
July 22 – Jan 24 (2 visits)
Period
Subcontract
JCT re-measure
Scope of Works
Construction of foul pump station including;
- 7.5m deep 2.4m dia wet well
- Inlet & valve chambers
- Foul drainage 5m deep
- 2no 16m long storage tanks 5m deep
- Brick perimeter wall & concrete yard slab
- Foul rising main, chambers and connection – 1km with significant existing services, working in lane closures on the A43
- Foul rising main connection into Anglian Water live foul sewer 6.5m deep
- Street lighting ducting, column sleeves and chambers (1600m)
- Footways (5000m2)
- Edgings (2500m)
Surface water outfalls;
- Gabion reno mattresses
- MSE flex bagwork headwalls