Nine Mile Ride Extension
Project details
Construction of new roundabout, tie ins and 1.5km of road.
Client / Contractor
Balfour Beatty
Programme
50 weeks
Location
Finchampstead, Wokingham
April 21 – April 22
Period
Subcontract
NEC Option B re-measure
Scope of Works
- Bulk earthworks and drainage to compound setup
- Earthworks to roundabout and roads
- Road construction
- Deep drainage foul and storm (1m to 5m deep approx. 3000m)
- 50 hour weekend road possession for Thames Water live foul connection
- Ducting
- Utility trenches
- Kerb & edgings
- Paving
- Tie in works
- Topsoiling