Nine Mile Ride Extension

Project details

Construction of new roundabout, tie ins and 1.5km of road.

Client / Contractor

Balfour Beatty

Programme

50 weeks

Location

Finchampstead, Wokingham

April 21 – April 22

Period
Subcontract

NEC Option B re-measure

Scope of Works
  • Bulk earthworks and drainage to compound setup
  • Earthworks to roundabout and roads
  • Road construction
  • Deep drainage foul and storm (1m to 5m deep approx. 3000m)
  • 50 hour weekend road possession for Thames Water live foul connection
  • Ducting
  • Utility trenches
  • Kerb & edgings
  • Paving
  • Tie in works
  • Topsoiling